Project Timeline

Construction is expected from mid-2026 to mid-2028.

 

Completed
N
Completed

Clearing / Pre-Stage Work

February 2026 – May 2026

Completed
I
Completed

M-39 at I-94 to Outer Drive

Temporary Shoulder Widening & Crossover Construction

May 2026 – June 2026

M-39 Logo

In Progress
I
In Progress

I-94 from I-275 to Michigan Ave. (US-12)

Temporary Shoulder Widening & Crossover Construction

May 2026 – July 2026

In Progress
I
In Progress

Northbound & Southbound M-39 at I-94 to Outer Drive

Construction over Ecorse River

June 2026 – Spring 2028

M-39 Logo

Upcoming
I
Upcoming

Eastbound I-94

I-275 to Michigan Ave. (US-12) Construction

Eastbound I-94 traffic will be shifted to Westbound I-94 in late July 2026

July 2026 – Summer 2027

Upcoming
I
Upcoming

M-39 at I-94 to Outer Drive

Median Construction

Spring 2028

M-39 Logo

Upcoming
I
Upcoming

Westbound I-94

I-275 to Michigan Ave. (US-12) Construction

Westbound I-94 traffic will be shifted to Eastbound I-94

Summer 2027 – Spring 2028

Upcoming
I
Upcoming

I-94 from I-275 to Michigan Ave. (US-12)

Median & Shoulder Construction

Spring 2028

Upcoming

Upcoming

Freeway Reopened to Traffic

Summer 2028

Upcoming

Upcoming

Landscaping and Punch List

Summer 2028 – Summer 2029

Project Timeline Accessibility Summary: Plain-Text Description

This plain text summary provides a simplified, linear version of the Restore 94 project timeline. It is designed to improve accessibility for users with visual or cognitive impairments, as well as those using screen readers or assistive technology. The information below removes visual elements and presents the full timeline in clear, easy-to-read text.