Project Timeline
Construction is expected from mid-2026 to mid-2028.
Completed
Completed
Clearing / Pre-Stage Work
February 2026 – May 2026
Completed
Completed
M-39 at I-94 to Outer Drive
Temporary Shoulder Widening & Crossover Construction
May 2026 – June 2026
![]()
In Progress
In Progress
I-94 from I-275 to Michigan Ave. (US-12)
Temporary Shoulder Widening & Crossover Construction
May 2026 – July 2026
![]()
In Progress
In Progress
Northbound & Southbound M-39 at I-94 to Outer Drive
Construction over Ecorse River
June 2026 – Spring 2028
![]()
Upcoming
Upcoming
Eastbound I-94
I-275 to Michigan Ave. (US-12) Construction
Eastbound I-94 traffic will be shifted to Westbound I-94 in late July 2026
July 2026 – Summer 2027
![]()
Upcoming
Upcoming
M-39 at I-94 to Outer Drive
Median Construction
Spring 2028
![]()
Upcoming
Upcoming
Westbound I-94
I-275 to Michigan Ave. (US-12) Construction
Westbound I-94 traffic will be shifted to Eastbound I-94
Summer 2027 – Spring 2028
![]()
Upcoming
Upcoming
I-94 from I-275 to Michigan Ave. (US-12)
Median & Shoulder Construction
Spring 2028
![]()
Upcoming
Upcoming
Freeway Reopened to Traffic
Summer 2028
Upcoming
Upcoming
Landscaping and Punch List
Summer 2028 – Summer 2029
Project Timeline Accessibility Summary: Plain-Text Description
This plain text summary provides a simplified, linear version of the Restore 94 project timeline. It is designed to improve accessibility for users with visual or cognitive impairments, as well as those using screen readers or assistive technology. The information below removes visual elements and presents the full timeline in clear, easy-to-read text.